Code Finder

Question:

Answer:

 

1. Is the equipment classified as a Nuclear Item (for a nuclear power plant)?

NO   
     
2. Does the equipment generate steam for use external to itself? YES  
     
3. Does the MAWP (Maximum Allowable Working Pressure) at the top of the equipment exceed 15 psi (1.03 bar), externally or internally with no limitation on size? YES  
     
4. Is the equipment directly fired, or electrically heated?

electrically heated

 
     

ASME Code Section I, Preamble
Manufacturer needs ASME Certificate " S-Stamp"
or
Section VIII, e.g. Div. 1 "Unfired Steam Boiler", please refer to (U-1(g))
Manufacturer needs ASME Certificate " U-Stamp"

   
     
 

Do you have any questions?

For further information visit the Discussion Forum or complete and submit this form. We will contact you to discuss your individual needs.

Name: 
Company:
Phone or E-Mail:
Comments:
   
 


sitemap | e-mail | imprint | phone: 0049-(0)201-89 00 90-0 | fax: 0049-(0)201-89 00 90-25 | © 1998 - 2008 ONE/TÜV/BV

ONE/TÜV/BV Technische Inspektions GmbH
Regional Office of OneBeacon America Insurance Company
Langemarckstr. 20
45141 Essen
Germany