PostPosted: Thu May 21, 2009 5:38 am 
Offline
----------------
----------------

Joined: Thu Apr 02, 2009 9:38 am
Posts: 59
Dear Sir,

My shell matrl is SA 387 Gr.11 Cl2. We have decided to weld all circumferential and longitudinal joints of shell courses with double welded butt joints (i.e. Double V)..

Problem lies where our fabricator approach the shell to tubesheet joint i.e. last joint of shell course and near to tubesheet joint.

Please advice if we can do a combination of weld joints i.e. all major joints of double V and two joints i.e. shell to tubesheet joints as single welded butt joints meeting criteria UW-35. Yes or No ?.

OR

I dont know if double welded joint is practically possible at this place i.e. shell to tubesheet joint location.

Shell thk = 30mm
Pressure = 33 kg/cm2g
Temperature = 450 deg. C
Matrl - SA-387 Gr. 11 CL2
Service is Fertilizer Process Gas (Shell and Tube sides are both with Process Gas)

_________________
Syed Osama Nusrat Ali
Exective Engineering (Project)
Fauji Fertilizer Company Limited
Pakistan
email: osama_ali@ffc.com.pk
Cell # +92-3025252018


Top
 Profile  
 
PostPosted: Thu May 21, 2009 8:35 pm 
Offline
----------------
----------------

Joined: Tue May 19, 2009 6:31 pm
Posts: 207
Location: Chicago, Illinois USA
Shell to tubesheet weld be made as full penetration butt weld and it will comply with the requirement UW-35.

leem817


Top
 Profile  
 
PostPosted: Tue May 26, 2009 6:27 am 
Offline
----------------
----------------

Joined: Thu Apr 02, 2009 9:38 am
Posts: 59
Please if someone can answer the below mentioned issue:

Our fabricator apprehension is that a double welded butt joint is difficult near the shell to tubesheet joint i.e. last joint of shell course.

Please advice if we can perform a combination of weld joints:

All shell course i.e. circumferential and longitudinal joints with double V and last joint (no approach after tubebundle insertion) as single welded butt joints meeting criteria UW-35.

Can we apply above fabrication technique - Yes or No ?
OR

_________________
Syed Osama Nusrat Ali
Exective Engineering (Project)
Fauji Fertilizer Company Limited
Pakistan
email: osama_ali@ffc.com.pk
Cell # +92-3025252018


Top
 Profile  
 
PostPosted: Wed May 27, 2009 9:33 am 
Offline
----------------
----------------
User avatar

Joined: Thu Dec 20, 2001 1:00 am
Posts: 26
Quote:
Please if someone can answer the below mentioned issue:

Our fabricator apprehension is that a double welded butt joint is difficult near the shell to tubesheet joint i.e. last joint of shell course.

Please advice if we can perform a combination of weld joints:

All shell course i.e. circumferential and longitudinal joints with double V and last joint (no approach after tubebundle insertion) as single welded butt joints meeting criteria UW-35.

Can we apply above fabrication technique - Yes or No ?
Yesprovide that the root pass of single V can visually inspection as required by UW-35 and the welding procedure shall qualify. Para UW-9 requireds the joint preparation of groove weld shall design such as to permit complete fusion and penetration so that it can be considered as type 1 of table UW-12.


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 4 posts ] 

All times are UTC + 2 hours


Who is online

Users browsing this forum: No registered users and 0 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Group

phpBB SEO