All times are UTC + 2 hours




Post new topic Reply to topic  [ 7 posts ] 
Author Message
PostPosted: Mon Jan 30, 2012 1:58 pm 
Offline

Joined: Fri Jan 27, 2012 3:28 pm
Posts: 3
Dear all,

I have a discussion with a PED Inspector regarding my calculation and drawings for a pressure vessel.
In the calculation I do not have included the DIN flanges, because it is a standard part and must not be calculated (my understanding, hopefully correct).
The drawing of this pressure vessel shows the DIN flanges and the DIN material, the rest parts (pipe, plate) are from ASME material.

Is there a rule, that I am not allowed to work with this material mixture?

The PED Inspector forces me to change the DIN material to ASME material, but the calculation is without these flanges.
What can I do to recieve my PED stamp without this discussions?

Thanks to all for your help.


Top
 Profile  
 
PostPosted: Wed Feb 01, 2012 7:57 am 
Offline
----------------
----------------

Joined: Tue Oct 03, 2006 7:01 am
Posts: 58
Main question is what is the design code?

regards,
malyl


Top
 Profile  
 
PostPosted: Mon Feb 06, 2012 10:20 am 
Offline
----------------
----------------
User avatar

Joined: Sun May 20, 2007 3:16 pm
Posts: 141
Location: Jord International-India
""In the calculation I do not have included the DIN flanges, because it is a standard part and must not be calculated (my understanding, hopefully correct).
""

How above could be ?

Flanges are also pressure parts in no case any inspector will allow to use compliance of thickness .

Rest is you will have to provide calculation / compliance as per PED inspecotr insisted.

_________________
Niraj


Top
 Profile  
 
PostPosted: Mon Feb 06, 2012 10:59 pm 
Offline
----------------
----------------
User avatar

Joined: Sat Dec 15, 2001 1:00 am
Posts: 657
Charsi wrote:
Dear all,

I have a discussion with a PED Inspector regarding my calculation and drawings for a pressure vessel.
In the calculation I do not have included the DIN flanges, because it is a standard part and must not be calculated (my understanding, hopefully correct).
The drawing of this pressure vessel shows the DIN flanges and the DIN material, the rest parts (pipe, plate) are from ASME material.

Is there a rule, that I am not allowed to work with this material mixture?

The PED Inspector forces me to change the DIN material to ASME material, but the calculation is without these flanges.
What can I do to recieve my PED stamp without this discussions?

Thanks to all for your help.


From the way you are placing your question, I understand the Code of construction is ASME VIII Div.1. If this is the case you have to use ASME material and standard flanges or calculate them per Appx.2
Mauro


Top
 Profile  
 
PostPosted: Tue Feb 07, 2012 1:39 am 
Offline
----------------
----------------
User avatar

Joined: Tue Mar 21, 2006 11:11 am
Posts: 480
Location: England
Quote:
If this is the case you have to use ASME material and standard flanges

Mauro, he HAS used standard flanges...
I know, I know, but this is a public forum, how do you know who reads it and how an ambiguous statement can be understood...

_________________
Konrad Anikiel


Top
 Profile  
 
PostPosted: Mon Feb 20, 2012 3:14 pm 
Offline

Joined: Fri Jun 06, 2008 2:57 pm
Posts: 9
Location: India
Hi!

My understanding is:

1. You want to use standard DIN flanges, i presume these have been manufactured using applicable DIN or DIN EN material.

2. These are Weld Neck or some other suitable type.

Ideally, you should not have a need to perform separate design calculations, mainly due to the following:

A. Code allows the use of welded standard pressure parts for use other than shell or head under UW-11(c). If the pressure temperature ratings are duly catalogued and the appropriate marking applied, you need not make seperate calculations.

B. If you are using Weld Neck flange, the code boundry limit has already terminated at the first cir-seam joint i.e. joint between the weld neck flange and the nozzle neck. See U-1(e)(1) of the code. Hence, the question of addressing the design of component, which is part of the piping system should not ideally arise.

C. The material (DIN or DIN EN standard) can always be re-certified by you in accordance with UG-10 requirements of the code, hence assigning P nos for welding should also not be an issue.

Hope i have not complicated it further for you.

Mayur


Top
 Profile  
 
PostPosted: Wed Feb 29, 2012 11:21 am 
Offline
----------------
----------------

Joined: Fri Jul 09, 2010 7:57 am
Posts: 79
Please see UG-11(d)


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 7 posts ] 

All times are UTC + 2 hours


Who is online

Users browsing this forum: No registered users and 0 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Group

phpBB SEO