All times are UTC + 2 hours




Post new topic Reply to topic  [ 9 posts ] 
Author Message
 Post subject: Ground flush
PostPosted: Wed Oct 26, 2011 6:03 pm 
Offline
----------------
----------------

Joined: Thu Oct 28, 2010 3:16 pm
Posts: 40
Dear experts,

Our designer specified certain welds shall be ground flush with the base material considering the function requirement,However the QC guys said we didn't tell them the tolerance for the ground,they means they can't perform and judge the "flush" condition. is that so? Do I need to specify a tolerance to them to perform the VT?

thanks in advance!


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Thu Oct 27, 2011 7:52 pm 
Offline
----------------
----------------
User avatar

Joined: Sat Dec 15, 2001 1:00 am
Posts: 657
Dephy wrote:
Dear experts,

Our designer specified certain welds shall be ground flush with the base material considering the function requirement,However the QC guys said we didn't tell them the tolerance for the ground,they means they can't perform and judge the "flush" condition. is that so? Do I need to specify a tolerance to them to perform the VT?

thanks in advance!

QC Guys are right.
mauro


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Tue Nov 01, 2011 3:48 pm 
Offline
----------------
----------------

Joined: Thu Oct 28, 2010 3:16 pm
Posts: 40
Gonzaga wrote:
Dephy wrote:
Dear experts,

Our designer specified certain welds shall be ground flush with the base material considering the function requirement,However the QC guys said we didn't tell them the tolerance for the ground,they means they can't perform and judge the "flush" condition. is that so? Do I need to specify a tolerance to them to perform the VT?

thanks in advance!

QC Guys are right.
mauro


thx,mauro,

i got the reply from the designer,they said the requirment is zero tolerance, no reinforcement,that really let me puzzled.


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Wed Nov 02, 2011 1:12 am 
Offline
----------------
----------------
User avatar

Joined: Sat Dec 15, 2001 1:00 am
Posts: 657
Dephy wrote:
Gonzaga wrote:
Dephy wrote:
Dear experts,

Our designer specified certain welds shall be ground flush with the base material considering the function requirement,However the QC guys said we didn't tell them the tolerance for the ground,they means they can't perform and judge the "flush" condition. is that so? Do I need to specify a tolerance to them to perform the VT?

thanks in advance!

QC Guys are right.
mauro


thx,mauro,

i got the reply from the designer,they said the requirment is zero tolerance, no reinforcement,that really let me puzzled.


Zero tolerance is not a technical answer.
Mauro


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Mon Nov 28, 2011 12:30 pm 
Offline
----------------
----------------

Joined: Sat Aug 27, 2011 9:46 am
Posts: 24
hi
i think in code they mensioed maximum Renforcement but Not mensioned Minimun I Think Minimum is zero and it is applicable for ground flush welding


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Tue Dec 06, 2011 12:25 am 
Offline
----------------
----------------
User avatar

Joined: Sat Dec 15, 2001 1:00 am
Posts: 657
pravin143 wrote:
hi
i think in code they mentioned maximum Reinforcement but Not mentioned minimum I think Minimum is zero and it is applicable for ground flush welding


OK, not very "technical". So we can say ground flush is flat with zero tolerance, that means flat like the plate can be.
BUT:
Impossible to obtain with a grinding machine.....manually operated.......unless we can tolerate a certain uneven.
Tolerate? do we mean we accept a tolerance?
The circle is closed.
Mauro


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Fri Dec 16, 2011 12:20 am 
Offline
----------------
----------------

Joined: Thu May 01, 2008 12:17 pm
Posts: 86
Location: Kazakhstan
ZERO tolerance is impossible. Flush needs to be better defined and what tools are appropriate for measurement. I'm sure we all understand the designer probably wants the weld ground as flat as the plate but as suggested, by using a manual grinding operation there may also be some base metal removed... naturally, base metal thickness has a manufacturing "tolerance" but need to go back again and get clearer definition of flush from the designer... does flush mean 0.0000000001 mm above surface? Who knows?


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Tue Jan 24, 2012 2:16 pm 
Offline

Joined: Tue Jan 24, 2012 12:00 pm
Posts: 4
Hey guys, I'm new to the forum, glad to be here and looking forward to getting to know you guys.

So here we go......I've been in the welding industry for around 30 years, everything to fish cookers to pressure vessels. I hold a CWI, ASNT NDT Level III VT, and an API 510. My question is recently the company I work for sent one of their design engineers for a "PE" cert. Since he got back weird things have been going on that I don't know if right or not. Most of the pipe fittings we build are to B31.1, B31.3, B31.4, B31.8, a few to API 1104. The other day while doing a visual weld inspection there was a 12" area that was slightly concave that I rejected. The "PE" said it was OK. I said it didn't meet the requirements of the code. He informed me that as a design engineer with a "PE" that he could override me and the code. Does this sound right? I have not read B31.3 in it's entity, what does it say about this? Any info would be great.
i think you will give me some thing reason able so please share some thing to me,,

_________________
ac repair houston


Top
 Profile  
 
 Post subject: Re: Ground flush
PostPosted: Tue Feb 14, 2012 4:59 pm 
Offline

Joined: Fri Feb 04, 2011 3:52 pm
Posts: 7
You cannot override or take exception to the Code unless he can show you where it says he can do so. Otherwise you can't certify it to those requirements.

Also, Flush is defined as being essentially even, but not below, the surface of the adjacent base material. Some codes allow you to be slightly under by whatever the undercut allowance is. I've seen a lot of customers specify what flush means, as it usually depends on service conditions, but typically is -0" to +1/16"


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 9 posts ] 

All times are UTC + 2 hours


Who is online

Users browsing this forum: No registered users and 0 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Group

phpBB SEO