NQA-1 edition1994
9S-1 Supplementary Requirements for Control of Processes
Code:
4 INSPECTION HOLD POINTS
If mandatory inspection hold points are required beyond which work shall not
proceed without the specific consent of the designated representative, the specific hold
points shall be indicated in appropriate documents. Consent to waive specified hold
points shall be recorded prior to continuation of work beyond the designated hold
point.
ASME NCA-2007+a08
ARTICLE NCA-9000 GLOSSARY
Code:
hold point: a designated stopping place during or following
a specific activity at which inspection or examination is
required before further work can be performed.
my question is that the designated Hold Poiont can be waived or not?
seemed that NCA and NQA-1 have a little different? which one will be taken precede?