 Post subject: MDR REQUIREMENT
PostPosted: Thu Oct 06, 2011 1:10 pm 
Offline

Joined: Thu Oct 06, 2011 12:58 pm
Posts: 1
Hello,

We are Manufacturers of Pressure parts and we are currently holding S Stamp. Now a customer has approached us for the manufacture of pressure parts. Design and major raw materials are in customer scope, in our scope there are some attachment raw materials and manufacturing. Customer is asking us to code stamp the components Wether we can take up the same.

KIndly reply.


Top
 Profile  
 
 Post subject: Re: MDR REQUIREMENT
PostPosted: Fri Oct 07, 2011 9:11 pm 
Offline
----------------
----------------
User avatar

Joined: Sat Dec 15, 2001 1:00 am
Posts: 657
mohanarengan wrote:
Hello,

We are Manufacturers of Pressure parts and we are currently holding S Stamp. Now a customer has approached us for the manufacture of pressure parts. Design and major raw materials are in customer scope, in our scope there are some attachment raw materials and manufacturing. Customer is asking us to code stamp the components Wether we can take up the same.

KIndly reply.


Briefly:
Your Customer probably is an Enginnering Co. and has no S Stamp (Engineering could have, for engineering only) and designs the complete boiler. You have in the scope of your certificate design as well. You should be able to verify the design of your client for conformity to Sect I, whilst your Customer has the experience of the thermodinamic design. The Engineering wants also to buy material for you.
Mind that you have the full responsibility for Code compliance of the complete boiler, including external piping, safety valves, and material. Assembly may be done by Assembler holding A or S stamp maybe or maybe not under your responsibility.
Contact your Agency.
MG


Top
 Profile  
 
 Post subject: Re: MDR REQUIREMENT
PostPosted: Sun Oct 09, 2011 8:28 am 
Offline
----------------
----------------
User avatar

Joined: Sat Dec 01, 2001 1:00 am
Posts: 869
Location: Essen, Germany
Mohanarengan,

I agree with Gonzaga.
Just let me add, the Code might permit you to stamp the complete boiler, but is your company prepared for this?

You need to review all calculations, and aprove them as your responsibility, please refer to your QCmanual, Design Chapter.

Your AI must perform his Design Review as well. Talk to him, what his questions are.

And you are responsible for the assembly as well. including the complete boiler hydrotest. Even if assembly is done by somebody else, you are still responsible to specify and control the field assembly.

Certainly your sales guys should make a new offer. This scenario happens frequently. Sometimes I have the feeling that some Engrg companies just look for a cheap stamp.

DK


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 3 posts ] 

All times are UTC + 2 hours


Who is online

Users browsing this forum: No registered users and 0 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Group

phpBB SEO