In the inquiry of CC 2235-9 is written "...an ultrasonic examination be used in lieu of radiography, when radiography is required in accordance with Section I, para. PW-11; Section VIII, Division 1, para. UW-11(a); Section VIII, Division 2, Table AF-241.1; and Section XII, TE-230.1?" In reply we see the words "Thickness of vessel and boiler", "vessel volume examined", "block Representing OD surface vessel," Representing block ID surface vessel ". Always the words of components “vessel”, “boiler” never once words “piping”. I know CC 181 cover piping for B31.3 Process Piping and CC 179 for piping B31.1. My question is: CC 2235-9 cover the piping that falls under Section I ? Many thanks for your reply. Mario
|