 Post subject: Preheat Temperature Range
PostPosted: Tue Nov 17, 2009 1:01 pm 
Offline
----------------
----------------

Joined: Thu Apr 02, 2009 9:38 am
Posts: 56
Dear Sir,

Base metal - SA 387 Gr 11 CL 2
P No. 4 & Gr No 1
Welding Processs = GTAW + SMAW (Root GTAW and rest SMAW)

Preheat parameters mentioned in PQR is as follows:

a) Preheat temperature = 250 deg C
b) Interpass temperature = 300 deg C Max
c) Intermediate Postheating = 350 deg C for 4 hr (Cooling under insulation)

Question:
How to review above a,b and c points according to ASME Sections as i have checked Appendix R i.e. R3 (ASME Section VIII Div 1), it only mentions 121 deg C preheat temperature for P No.4 and Gr.1.

Appreciate detailed reply, please

Best regards
Osama

_________________
Syed Osama Nusrat Ali
Project Engineer
Fauji Fertilizer Company Limited
Pakistan
email: osama_ar@yahoo.com
Cell # +92-3025252018


Top
 Profile  
 
 Post subject: Re: Preheat Temperature Range
PostPosted: Wed Nov 18, 2009 5:37 am 
Offline
----------------
----------------

Joined: Thu Apr 02, 2009 9:38 am
Posts: 56
Waiting for anyone to reply my query.

Do i have something which no one can comment.

_________________
Syed Osama Nusrat Ali
Project Engineer
Fauji Fertilizer Company Limited
Pakistan
email: osama_ar@yahoo.com
Cell # +92-3025252018


Top
 Profile  
 
 Post subject: Re: Preheat Temperature Range
PostPosted: Wed Dec 02, 2009 4:05 pm 
Offline
----------------
----------------

Joined: Thu Aug 21, 2008 9:08 am
Posts: 33
You need to note that Appendix R is non mandetory and to be used as a guidance. Normally Sa 387 Gr 11 Class 2 needs pre heating. You have not specified thickness under consideraion. Remember that Section IX allows pre heat temperature 55 Deg C less in Production WPS than what is used while welding PQR test coupon. Hence if you apply 250 Deg C then u need to do minimum 195 Deg C in Production WPS. So I need to know the hickness involved and 121 Deg C sounds well.

When you are doing pre heating and thickness is not that high then I dont think you need intermediae postheating. You may refer UCS 56 tables to know PWHT requirement since WPS shall essentially meet Construction Code requirement and not of Section IX which is a reference book. Please let me know thickness so that I can put my views more clearly.

Surendra Ghate
+919725014766

Base metal - SA 387 Gr 11 CL 2
P No. 4 & Gr No 1
Welding Processs = GTAW + SMAW (Root GTAW and rest SMAW)

Preheat parameters mentioned in PQR is as follows:

a) Preheat temperature = 250 deg C
b) Interpass temperature = 300 deg C Max
c) Intermediate Postheating = 350 deg C for 4 hr (Cooling under insulation)

Question:
How to review above a,b and c points according to ASME Sections as i have checked Appendix R i.e. R3 (ASME Section VIII Div 1), it only mentions 121 deg C preheat temperature for P No.4 and Gr.1.

Appreciate detailed reply, please

Best regards
Osama[/quote]


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 3 posts ] 

All times are UTC + 2 hours


Who is online

Users browsing this forum: No registered users and 0 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB © 2000, 2002, 2005, 2007 phpBB Group

phpBB SEO